The Ministry for the Ecological Transition sent to the State Council on November 24, 2020 the Draft Royal Decree on Access and Connection to the Council.

One of the most substantial changes will be related to the definition of the installed power. The Royal Decree Project will approve that the installed power is the sum of the capacity of the investors. This modification will promote the installation of bifacial panels in future photovoltaic projects. In addition to this change, there will be some more modifications regarding new grid applications, possible grid acces tenders and the elimination of the “Single Node Contact Person” (IUN)